When the project runs long: terms and extensions
Rehabs and builds can run past the original schedule. Here is what each short-term program publishes about term length, longer terms and extensions.

Projects run long. A permit takes longer than planned, a contractor falls behind, a sale takes more time. Here is what our short-term programs publish about term length and extensions.
Fix & Flip
The term is 12 months. Expansion, addition, conversion and ADU projects can run 18 to 24 months, with a pricing adjustment.
Stabilized Bridge
The term is 12 months. Extensions of up to 50% of the original term are available, for a fee.
Ground-Up Construction
The term is 12 months. 18 to 24 months is available with a pricing adjustment. Extensions of up to 50% of the original term are available, for a fee.
The long-term loans
The Rental Loan and Rental Portfolio have a 30-year term, so this does not apply to them.
What this means for your plan
All three short-term loans are interest only with a balloon at maturity. That balloon is the date you plan around. If the schedule slips, an extension costs money, and an exit you planned for month 12 now has to hold at month 15 or 18.
What to do (general advice)
- Set your schedule with slack built in.
- If the project is likely to need more than 12 months, say so when you send the scenario. Do not wait until month 11.
- Keep your exit lined up, whether that is a sale or a refinance. Check the seasoning rules for the long-term loan, since they are counted from your purchase date.
What to send us
The property, the scope of work, your schedule and your exit plan. Send it as a scenario. It is a preliminary inquiry only. Pricing is quoted per deal.